A resource constrained scheduling problem with multiple independent producers and a single linking constraint: a coal supply chain example
DOI10.1016/J.EJOR.2013.10.006zbMATH Open1304.90105OpenAlexW2039044958MaRDI QIDQ2514747FDOQ2514747
Authors: Anu Thomas, Jayendran Venkateswaran, Gaurav Singh, Mohan Krishnamoorthy
Publication date: 3 February 2015
Published in: European Journal of Operational Research (Search for Journal in Brave)
Full work available at URL: https://doi.org/10.1016/j.ejor.2013.10.006
Recommendations
- Resource constraint scheduling with a fractional shared resource
- Rail schedule optimisation in the hunter valley coal chain
- A new constraint programming approach for optimising a coal rail system
- Using column generation to solve a coal blending problem
- Supply chain optimization in the pulp mill industry -- IP models, column generation and novel constraint branches.
column generationdistributed decision makingjob schedulingcoordinated schedulingresource constrained scheduling
Deterministic scheduling theory in operations research (90B35) Case-oriented studies in operations research (90B90)
Cites Work
- Title not available (Why is that?)
- Selected Topics in Column Generation
- Production Planning by Mixed Integer Programming
- Title not available (Why is that?)
- A Primer in Column Generation
- Mathematical Programs with Optimization Problems in the Constraints
- Complex Scheduling
- Decomposition Principle for Linear Programs
- The volume algorithm: Producing primal solutions with a subgradient method
- A mixed integer programming model for long term capacity expansion planning: a case study from the Hunter valley coal chain
- Reformulation and decomposition of integer programs
- Cover and pack inequalities for (mixed) integer programming
- A column generation approach to the heterogeneous fleet vehicle routing problem
- A column generation approach to airline crew scheduling
- On the choice of explicit stabilizing terms in column generation
- Combining Column Generation and Lagrangian Relaxation
- An algorithm for large scale 0-1 integer programming with application to airline crew scheduling
- Solving a resource allocation problem in wireless mesh networks: a comparison between a CP-based and a classical column generation
- Hierarchical production planning and scheduling in make-to-order environments: reaching short and reliable delivery dates
- A hierarchical bicriterion approach to integrated process plan selection and job shop scheduling
Cited In (4)
- A review of decentralized optimization focused on information flows of decomposition algorithms
- Coordination mechanisms with mathematical programming models for decentralized decision-making: a literature review
- Using column generation to solve a coal blending problem
- A column-generation-based algorithm for a resource-constrained project scheduling problem with a fractional shared resource
This page was built for publication: A resource constrained scheduling problem with multiple independent producers and a single linking constraint: a coal supply chain example
Report a bug (only for logged in users!)Click here to report a bug for this page (MaRDI item Q2514747)