A New Approach to Find Project Characteristics and Multiple Possible Critical Paths in a Fuzzy Project Network
From MaRDI portal
Publication:5216837
DOI10.1007/s12543-013-0133-5zbMath1430.90173OpenAlexW1964910982MaRDI QIDQ5216837
Publication date: 20 February 2020
Published in: Fuzzy Information and Engineering (Search for Journal in Brave)
Full work available at URL: https://doi.org/10.1007/s12543-013-0133-5
fuzzy PERTrooted treetrapezoidal fuzzy numbersearliest and latest timespossible critical pathstotal float
Cites Work
- Unnamed Item
- Unnamed Item
- Applying fuzzy method for measuring criticality in project network
- A subjective approach for ranking fuzzy numbers
- Fuzzy sets and systems. Theory and applications
- The use of fuzzy variables in PERT
- A procedure for ordering fuzzy subsets of the unit interval
- Using fuzzy set theory in a scheduling problem: A case study
- A new approach for ranking fuzzy numbers by distance method
- Fuzzy critical path method based on signed-distance ranking and statistical confidence-interval estimates
- Ranking fuzzy numbers with an area between the centroid point and original point.
- Modeling uncertain activity duration by fuzzy number and discrete-event simulation
- On computing the latest starting times and floats of activities in a network with imprecise durations
- Comparison of fuzzy numbers using a fuzzy distance measure
- On latest starting times and floats in activity networks with ill-known durations
- Selecting IS personnel use fuzzy GDSS based on metric distance method
- A Network Flow Computation for Project Cost Curves
- Fuzzy-Network Planning - FNET
- A new approach to handling fuzzy decision-making problems
- Application of a Technique for Research and Development Program Evaluation
- Fuzzy sets
- Reasonable properties for the ordering of fuzzy quantities. I
- Reasonable properties for the ordering of fuzzy quantities. II
- Critical path analysis in the network with fuzzy activity times
This page was built for publication: A New Approach to Find Project Characteristics and Multiple Possible Critical Paths in a Fuzzy Project Network