scientific article; zbMATH DE number 3843474
A time scheduling problem is studied involving n operations and m machines. Each operation can be performed on any machine. Sequential relations among operations are described by an oriented graph G with number of nodes equal to the number of operations (an arc from a node u to a node v means that operation v could be started only after operation u is finished). It is supposed that processing time for each operation on any machine is equal to 1. In general the problem of finding an optimal schedule (minimizing total processing time) is NP-complete. The author gives simple formulas for evaluating lower bounds of the length (total processing time) of feasible schedules under various assumptions on the graph G.