Recent results on resource-constrained project scheduling with time windows: Models, solution methods, and applications (Q1854657)

From MaRDI portal

!

This is the item page for this Wikibase entity, intended for internal use and editing purposes. Please use the normal view instead:

scientific article; zbMATH DE number 1854303
Language Label Description Also known as
default for all languages
No label defined
    English
    Recent results on resource-constrained project scheduling with time windows: Models, solution methods, and applications
    scientific article; zbMATH DE number 1854303

      Statements

      Recent results on resource-constrained project scheduling with time windows: Models, solution methods, and applications (English)
      0 references
      0 references
      0 references
      0 references
      10 April 2003
      0 references
      The paper surveys results on deterministic resource-constrained project scheduling problems with general temporal constraints and different regular and nonregular objective functions. After presenting a basic formulation of the problem (incorporating renewable resources and minimal and maximal time-lags between the activities), structural questions of feasible schedules are investigated. Based on these structures, different exact and heuristic algorithms are discussed. Afterwards extensions of the basic model are presented (calendarization, storage resources, sequence-dependent changeover times, non-renewable resources and multi-mode activities). Finally, it is shown how the considered models can be applied in make-to-order production, batch scheduling in process industries and investment projects.
      0 references
      0 references
      resource-constrained project scheduling
      0 references
      regular and nonregular objective functions
      0 references
      exact algorithms
      0 references
      heuristics
      0 references
      applications
      0 references