Scheduling under uncertainty: Bounding the makespan distribution

From MaRDI portal





This paper investigates and reviews techniques for taking into account randomness in project scheduling. Particularly the makespan, i.e., the earliest project completion is of interest. Because of the high complexity of the problem, it is unlikely that it can be solved exactly, therefore, approximations or bounds are offered in literature. General bounds and more specific bounds are introduced and analyzed. Some computational experiences with various bounds conclude the paper. For the entire collection see [Zbl 0978.00022].