Maximizing the net present value of a project under uncertainty: activity delays and dynamic policies
From MaRDI portal
Publication:6572829
DOI10.1016/J.EJOR.2024.03.029MaRDI QIDQ6572829FDOQ6572829
Stefan Creemers, Roel Leus, Salim Rostami
Publication date: 16 July 2024
Published in: European Journal of Operational Research (Search for Journal in Brave)
Cites Work
- Procedures for resource leveling and net present value problems in project scheduling with general temporal and resource constraints
- Proactive policies for the stochastic resource-constrained project scheduling problem
- Critical-Path Planning and Scheduling: Mathematical Basis
- Application of a Technique for Research and Development Program Evaluation
- Maximizing the net present value of a project under uncertainty
- New strategies for stochastic resource-constrained project scheduling
- Solving stochastic resource-constrained project scheduling problems by closed-loop approximate dynamic programming
- New competitive results for the stochastic resource-constrained project scheduling problem: exploring the benefits of pre-processing
- Sharp Bounds on the Value of Perfect Information
- Cash Flows in Networks
- An optimization model for stochastic project networks with cash flows
- Scheduling Markovian PERT networks to maximize the net present value
- Activity Delay in Stochastic Project Networks
- Scheduling Markovian PERT networks to maximize the net present value: new results
- Minimizing the expected makespan of a project with stochastic activity durations under resource constraints
- The payment scheduling problem
- A steepest ascent approach to maximizing the net present value of projects
- A perfect information lower bound for robust lot-sizing problems
- Maximizing the expected net present value of a project with phase-type distributed activity durations: an efficient globally optimal solution procedure
- Moments and distribution of the net present value of a serial project
This page was built for publication: Maximizing the net present value of a project under uncertainty: activity delays and dynamic policies
Report a bug (only for logged in users!)Click here to report a bug for this page (MaRDI item Q6572829)