Multimode preemptive resource investment problem subject to due dates for activities: formulation and solution procedure
From MaRDI portal
Publication:471724
DOI10.1155/2014/740670zbMath1302.90074OpenAlexW1968865274WikidataQ59047896 ScholiaQ59047896MaRDI QIDQ471724
Behrouz Afshar-Nadjafi, Mohammad Arani
Publication date: 17 November 2014
Published in: Advances in Operations Research (Search for Journal in Brave)
Full work available at URL: https://doi.org/10.1155/2014/740670
Mixed integer programming (90C11) Deterministic scheduling theory in operations research (90B35) Production theory, theory of the firm (91B38) Resource and cost allocation (including fair division, apportionment, etc.) (91B32)
Cites Work
- Unnamed Item
- Multi-mode resource-constrained project scheduling using RCPSP and SAT solvers
- Properties of optimal schedules in preemptive shop scheduling
- A double genetic algorithm for the MRCPSP/max
- A neurogenetic approach for the resource-constrained project scheduling problem
- Preemption in single machine earliness/tardiness scheduling
- Experimental investigation of heuristics for resource-constrained project scheduling: an update
- A genetic algorithm for resource investment project scheduling problem, tardiness permitted with penalty
- Linear programming based algorithms for preemptive and non-preemptive RCPSP
- An exact algorithm for minimizing resource availability costs in project scheduling
- A survey of variants and extensions of the resource-constrained project scheduling problem
- A new model for the preemptive earliness-tardiness scheduling problem
- A genetic algorithm for the preemptive and non-preemptive multi-mode resource-constrained project scheduling problem
- Scheduling subject to resource constraints: Classification and complexity
- An efficient optimal solution procedure for the preemptive resource-constrained project scheduling problem
- An exact algorithm for project scheduling with multiple modes
- ProGen/\(\pi x\) -- An instance generator for resource-constrained project scheduling problems with partially renewable resources and further extensions
- Experimental evaluation of state-of-the-art heuristics for the resource-constrained project scheduling problem
- An effective shuffled frog-leaping algorithm for resource-constrained project scheduling problem
- Properties of multi-mode resource-constrained project scheduling problems with resource vacations and activity splitting
- A combinatorial particle swarm optimization for solving multi-mode resource-constrained project scheduling problems
- Solving the resource availability cost problem in project scheduling by path relinking and genetic algorithm
- Pre-emption in resource-constrained project scheduling
- A hybrid scatter search for the discrete time/resource trade-off problem in project scheduling
- Scatter search for project scheduling with resource availability cost
- A Branch-and-Cut Procedure for the Multimode Resource-Constrained Project-Scheduling Problem
- Minimizing Costs of Resource Requirements in Project Networks Subject to a Fixed Completion Time
- Optimization guided lower and upper bounds for the resource investment problem
- Minimizing Resource Availability Costs in Time-Limited Project Networks
- An exact procedure for the resource-constrained weighted earliness-tardiness project scheduling problem
This page was built for publication: Multimode preemptive resource investment problem subject to due dates for activities: formulation and solution procedure