Simulated annealing and tabu search for multi-mode resource-constrained project scheduling with positive discounted cash flows and different payment models

From MaRDI portal
Publication:1767683

DOI10.1016/j.ejor.2003.10.053zbMath1061.90048OpenAlexW1989154340MaRDI QIDQ1767683

Grzegorz Waligóra, Marek Mika, Jan Weglarz

Publication date: 8 March 2005

Published in: European Journal of Operational Research (Search for Journal in Brave)

Full work available at URL: https://doi.org/10.1016/j.ejor.2003.10.053




Related Items (27)

A scatter search heuristic for maximising the net present value of a resource-constrained project with fixed activity cash flowsThe impact of solution representations on heuristic net present value optimization in discrete time/cost trade-off project scheduling with multiple cash flow and payment modelsMulti-mode resource availability cost problem with recruitment and release dates for resourcesWhich fuzzy ranking method is best for maximizing fuzzy net present value?Comparative Analysis of Some Metaheuristics for Discrete-Continuous Project Scheduling with Activities of Identical Processing RatesVariable neighbourhood search and tabu search for a discrete time/cost trade-off problem to minimize the maximal cash flow gapPriority rule-based heuristic for multi-mode resource-constrained project scheduling problems with resource vacations and activity splittingA Petri net-based framework for realistic project management and scheduling: an application in animation and videogamesScheduling multi-mode projects under uncertainty to optimize cash flows: a Monte Carlo ant colony system approachProject scheduling with finite or infinite number of activity processing modes -- a surveyR\&D pipeline management: task interdependencies and risk managementAn applicable method for modifying over-allocated multi-mode resource constraint schedules in the presence of preemptive resourcesA lexicographic approach to the robust resource-constrained project scheduling problemMulti-objective multi-mode resource constrained project scheduling problem using Pareto-based algorithmsDiscrete-continuous project scheduling with discounted cash flows - a tabu search approachOptimizing version release dates of research and development long-term processesResource constrained project scheduling subject to due dates: preemption permitted with penaltyMulti-mode resource-constrained project scheduling problem with material ordering under bonus-penalty policiesMetaheuristics for multi-mode capital-constrained project payment schedulingMulti-mode project payment scheduling problems with bonus-penalty structureOptimization and analysis of the profitability of tariff structures with two-part tariffsTheoretical aspects of multicriteria flight gate scheduling: Deterministic and fuzzy modelsA survey of variants and extensions of the resource-constrained project scheduling problemClient‐contractor bargaining on net present value in project scheduling with limited resourcesSimulated annealing for financing cost distribution based project payment scheduling from a joint perspectiveDiscrete-continuous project scheduling with discounted cash inflows and various payment models -- a review of recent resultsSimulated annealing and tabu search for multi-mode project payment scheduling


Uses Software


Cites Work


This page was built for publication: Simulated annealing and tabu search for multi-mode resource-constrained project scheduling with positive discounted cash flows and different payment models