An updated survey of variants and extensions of the resource-constrained project scheduling problem
From MaRDI portal
Publication:2242185
DOI10.1016/j.ejor.2021.05.004zbMath1487.90294MaRDI QIDQ2242185
Publication date: 9 November 2021
Published in: European Journal of Operational Research (Search for Journal in Brave)
Full work available at URL: https://doi.org/10.1016/j.ejor.2021.05.004
90B35: Deterministic scheduling theory in operations research
90B10: Deterministic network models in operations research
90-02: Research exposition (monographs, survey articles) pertaining to operations research and mathematical programming
Related Items
Optimization Strategies for Resource-Constrained Project Scheduling Problems in Underground Mining, Application of idempotent algebra methods in genetic algorithm for solving the scheduling problem, R-SALSA: a branch, bound, and remember algorithm for the workload smoothing problem on simple assembly lines, New pseudo polynomial algorithms for a partial resource-constrained project scheduling problem, Literature reviews in operations research: a new taxonomy and a meta review, Project scheduling problem with fuzzy activity durations: a novel operational law based solution framework, Multi-project scheduling: a benchmark analysis of metaheuristic algorithms on various optimisation criteria and due dates, Resource-constrained multi-project scheduling problem: a survey, Tabu search for dedicated resource-constrained multiproject scheduling to minimise the maximal cash flow gap under uncertainty, MIP heuristics for a resource constrained project scheduling problem with workload stability constraints, Continuous-time formulations for multi-mode project scheduling, New resource-constrained project scheduling instances for testing (meta-)heuristic scheduling algorithms, A tree search heuristic for the resource constrained project scheduling problem with transfer times
Uses Software
Cites Work
- Providing Lower Bounds for the Multi-Mode Resource-Constrained Project Scheduling Problem
- Multiobjective model for solving resource‐leveling problem with discounted cash flows
- A multiobjective hybrid ant colony optimization approach applied to the assignment and scheduling problem
- A review of the contribution of operational research to project management
- Integrated time–cost tradeoff and resources leveling problems with allowed activity splitting
- An iterative time‐bucket refinement algorithm for a high‐resolution resource‐constrained project scheduling problem
- Modeling frameworks for the multi‐skill resource‐constrained project scheduling problem: a theoretical and empirical comparison
- Multi‐mode resource‐constrained project scheduling using modified variable neighborhood search heuristic
- On the efficient modeling and solution of the multi-mode resource-constrained project scheduling problem with generalized precedence relations
- A flow-based tabu search algorithm for the RCPSP with transfer times
- A rough-cut capacity planning model with overlapping
- Resource levelling in project scheduling with generalized precedence relationships and variable execution intensities
- An automatic algorithm selection approach for the multi-mode resource-constrained project scheduling problem
- MIP models for resource-constrained project scheduling with flexible resource profiles
- An integer programming approach to the multimode resource-constrained multiproject scheduling problem
- An effective branch-and-price algorithm for the preemptive resource constrained project scheduling problem based on minimal interval order enumeration
- A branch-price-and-cut algorithm for multi-mode resource leveling
- Scheduling resource-constrained projects with a flexible project structure
- An approach using SAT solvers for the RCPSP with logical constraints
- Integration of electromagnetism with multi-objective evolutionary algorithms for RCPSP
- Models and solution procedures for the resource-constrained project scheduling problem with general temporal constraints and calendars
- A multi-objective imperialist competitive algorithm for solving discrete time, cost and quality trade-off problems with mode-identity and resource-constrained situations
- Multi-mode resource-constrained project scheduling problems with non-preemptive activity splitting
- Solving software project scheduling problems with ant colony optimization
- Modeling and optimizing the evacuation of hospitals based on the MRCPSP with resource transfers
- Using resource scarceness characteristics to solve the multi-mode resource-constrained project scheduling problem
- Multi-mode resource-constrained project scheduling using RCPSP and SAT solvers
- An effective shuffled frog-leaping algorithm for multi-mode resource-constrained project scheduling problem
- Production scheduling with alternative process plans
- Time and work generalised precedence relationships in project scheduling with pre-emption: an application to the management of service centres
- An exact algorithm to minimize the makespan in project scheduling with scarce resources and generalized precedence relations
- Project scheduling with flexible resources: formulation and inequalities
- Branch-and-price approach for the multi-skill project scheduling problem
- A note on ``Branch-and-price approach for the multi-skill project scheduling problem
- Time symmetry of resource constrained project scheduling with general temporal constraints and take-give resources
- Multi-mode resource-constrained project scheduling problem with material ordering under bonus-penalty policies
- Heuristic approaches to discrete-continuous project scheduling problems to minimize the makespan
- Project scheduling with finite or infinite number of activity processing modes -- a survey
- Dismantling of nuclear power plants at optimal NPV
- An evolutionary algorithm for the resource-constrained project scheduling problem with minimum and maximum time lags
- Scheduling and constraint propagation
- A new lower bound for the resource-constrained project scheduling problem with generalized precedence relations
- A double genetic algorithm for the MRCPSP/max
- Theoretical and practical fundamentals for multi-objective optimisation in resource-constrained project scheduling problems
- Reactive scheduling in the multi-mode RCPSP
- Time-constrained project scheduling with adjacent resources
- Discrete-continuous project scheduling with discounted cash inflows and various payment models -- a review of recent results
- Minimizing the completion time of a project under resource constraints and feeding precedence relations: a Lagrangian relaxation based lower bound
- Experimental investigation of heuristics for resource-constrained project scheduling: an update
- Multi-objective decision analysis for competence-oriented project portfolio selection
- An exact algorithm for minimizing resource availability costs in project scheduling
- A survey of variants and extensions of the resource-constrained project scheduling problem
- An efficient genetic algorithm to maximize net present value of project payments under inflation and bonus-penalty policy in resource investment problem
- A genetic algorithm for the preemptive and non-preemptive multi-mode resource-constrained project scheduling problem
- Discrete time/cost trade-off problem: a decomposition-based solution algorithm for the budget version
- Scheduling non-professional table-tennis leagues
- A priority-rule method for project scheduling with work-content constraints
- Scheduling subject to resource constraints: Classification and complexity
- Stochastic project networks. Temporal analysis, scheduling and cost minimization
- Resource-constrained project scheduling: A survey of recent developments.
- Experimental evaluation of state-of-the-art heuristics for the resource-constrained project scheduling problem
- A heuristic procedure to solve the project staffing problem with discrete time/resource trade-offs and personnel scheduling constraints
- A tabu search procedure for the resource-constrained project scheduling problem with alternative subgraphs
- The impact of solution representations on heuristic net present value optimization in discrete time/cost trade-off project scheduling with multiple cash flow and payment models
- Multi-mode resource availability cost problem with recruitment and release dates for resources
- A path-relinking algorithm for the multi-mode resource-constrained project scheduling problem
- Resource-constrained project scheduling with flexible resource profiles in continuous time
- A biased random-key genetic algorithm for the project scheduling problem with flexible resources
- An efficient genetic algorithm to solve the resource-constrained project scheduling problem with transfer times: the single mode case
- Lower bounds for the event scheduling problem with consumption and production of resources
- Using constraint programming for solving RCPSP/MAX-cal
- A list-scheduling heuristic for the short-term planning of assessment centers
- Recursive logic-based Benders' decomposition for multi-mode outpatient scheduling
- A multi-threaded local search algorithm and computer implementation for the multi-mode, resource-constrained multi-project scheduling problem
- Capital- and resource-constrained project scheduling with net present value optimization
- An effective heuristic for project scheduling with resource availability cost
- Generic negotiation mechanisms with side payments -- design, analysis and application for decentralized resource-constrained multi-project scheduling problems
- A hybrid metaheuristic for resource-constrained project scheduling with flexible resource profiles
- Mixed-integer linear programming and constraint programming formulations for solving resource availability cost problems
- Optimal project duration for resource leveling
- An integer programming formulation for the project scheduling problem with irregular time-cost tradeoffs
- Project scheduling under uncertainty: survey and research potentials
- Minimizing total weighted late work in the resource-constrained project scheduling problem
- Resource-constrained project scheduling: Notation, classification, models, and methods
- Mixed-integer linear programming for resource leveling problems
- Optimizing the supply chain configuration for make-to-order manufacturing
- Minimizing the completion time of a project under resource constraints and feeding precedence relations: an exact algorithm
- Integrated scheduling and batch ordering for construction project
- Resource-constrained project scheduling with activity splitting and setup times
- Improved selection in evolutionary multi-objective optimization of multi-skill resource-constrained project scheduling problem
- A satisfiability and workload-based exact method for the resource constrained project scheduling problem with generalized precedence constraints
- Integration of routing into a resource-constrained project scheduling problem
- A branch-and-bound procedure for the resource-constrained project scheduling problem with partially renewable resources and general temporal constraints
- Multi-objective multi-mode resource constrained project scheduling problem using Pareto-based algorithms
- An experimental investigation of metaheuristics for the multi-mode resource-constrained project scheduling problem on new dataset instances
- Multi-objective metaheuristic algorithms for the resource-constrained project scheduling problem with precedence relations
- A hybrid rank-based evolutionary algorithm applied to multi-mode resource-constrained project scheduling problem
- A survey of hybrid metaheuristics for the resource-constrained project scheduling problem
- Strong bounds for resource constrained project scheduling: preprocessing and cutting planes
- Schedule generation scheme for solving multi-mode resource availability cost problem by modified particle swarm optimization
- A metaheuristic solution approach for the time-constrained project scheduling problem
- Solving RCPSP/max by lazy clause generation
- Multi-mode resource constrained multi-project scheduling and resource portfolio problem
- A lexicographic approach to the robust resource-constrained project scheduling problem
- A scatter search heuristic for maximising the net present value of a resource-constrained project with fixed activity cash flows
- An efficient metaheuristic for integrated scheduling and staffing IT projects based on a generalized minimum cost flow network
- Solving multi-mode time–cost–quality trade-off problems under generalized precedence relations
- A Hybrid Metaheuristic for the Multi-mode Resource Investment Problem with Tardiness Penalty